
The
century-old deep level gold mine located on the Witwatersrand Basin
at Boksburg – East Rand Proprietary Mines (ERPM) – has
been managed by Durban Roodepoort Deep (DRD) since it was purchased
by Crown Gold Recoveries (CGR), held 60% by Khumo Bathong Holdings
(KBH) and 40% by DRD, in November 2002.
As the driving force behind DRD’s empowerment
arm – KBH – CGR treats surface assets, known collectively
as Crown Central. For CGR, the year under review was dominated by
the purchase of the entity by KBH. Throughout this period, CGR has
put in a solid performance, with improvements in gold production,
from 4 312 kilograms (138 634 ounces) during
FY2002 to 4 389 kilograms (141 109 ounces) in
FY2003. Working profit after capex rose by 14%, despite an increase
in working cost of 16%. Costs were severely influenced by the depreciation
of the Rand.
Explains Grant Dempsey, divisional director:
Crown JV, “For ERPM, the period under review can only be described
as 'challenging'. Not only was the mine’s ownership and

management
team changed in October 2002, but the operation experienced labour
unrest in the form of the Cosatu strike in October 2002 and an underground
fire which continued for over a month in February 2003. Despite
total production losses of around 130 kilograms (4 180 ounces)
of gold and a total cost to the company of R15 million (US$1.83
million) after the fire, a return to steady state production was
achieved ahead of schedule in June 2003.”
With a purchase price tag of R100 million,
ERPM was anticipated to provide a particularly cheap source of new
gold for DRD, with costs of $12 per reserve ounce and $3 per resource
ounce. And admittedly, there have been many challenges in achieving,
let alone maintaining, these. As one of the oldest operating mines
in South Africa (production started in 1891), it is also one of
the deepest at some 3 000 metres below surface.
Currently the only mine pumping the West Wits
Basin, ERPM is burdened with high pumping costs – a direct
result of pumping old, defunct mines. Combine that with the high
maintenance costs associated with old shaft infrastructure and economically
challenging times on a global scale and it isn’t surprising
ERPM has been struggling over the last decade to survive (the company
was liquidated by the previous owners in 1999).
Says Dempsey, “But kudos must be given
where kudos is due. ERPM has been – and is – doing everything
in its power to not only survive but deliver on the performance
it is capable of.” With its actively involved empowerment
partner – KBH – CGR saw the potential that ERPM had
to offer, namely:
 |
A substantial ore reserve; |
 |
Plenty of gold in situ; |
 |
The fact that DRD’s Argonaut reserve
is only accessible from ERPM; and |
 |
The opportunity to purchase contiguous
ground on ERPM’s western perimeter which represents
further sound reserves. |
“Much of this potential is already being
realised. The company has made major inroads with regard to cost
control and productivity improvements,” adds Dempsey. Where
previous productivity statistics revealed an average of around 10
tons per total employee costed (tec), current levels are in the
region of 18 tons per tec. These improvements are largely the
result of the right sizing process earlier in 2003, which saw a
38% reduction in the labour force. Understandably, infrastructure
upgrades further contributed to the improvements aimed at sustaining
production at ERPM.
In an effort to meet scorecard criteria, ERPM
is actively seeking to employ previously disadvantaged members of
society; currently the mine employs two women with blasting certificates
and a full programme intended to develop historically disadvantaged
South Africans (HDSAs) within various disciplines including geology,
engineering, and communication and environment, is currently being
developed.
Of utmost importance are the surface synergies
which exist between CGR and ERPM. The Cason Dump is a case in point.
Bringing its reprocessing expertise to the table, and the sharing
of management functions, CGR can assist ERPM in turning the Cason
Dump to account.
On the topic of management, a new team has been
specifically chosen to turn the ERPM operation around, with the
back-up and support of an experienced group of mentors at DRD.
Going forward, the primary focus will be on maintaining
production such that sustainable profits become a reality. But the
management team realises that to do this it will need a focused,
integrated and motivated workforce, and surrounding communities
that want to work with rather than against the mine.